Project

A 48-inch onshore gas transmission line, around 878 km long, at about 95 bar.

Root Pass

The root of each joint was welded with TIG or MMA, depending on the procedure.

Fill & Cap

Fill and cap passes were welded with E8018 low-hydrogen basic electrodes.

Teamwork

Two welders worked on each joint to keep pace with the pipeline schedule.

Checks

Penetrant and ultrasonic testing of the welds to the project requirements.